Currently working on hull #52.
lamination of the FRP hull
lamination of the superstructure
Pre-plumbing and wiring
Installation of water, fuel and holding tanks
Installation of engines, shafts
and steering mechanisms
Installation of generator
Installation of the walls, beds,
counters etc. that were pre-fabricated
during the previous 9 weeks
Superstructure is lifted and
attached to the hull
Pre-wiring for all outlets, equipment
and lights
Plumbing
Installation of flooring
Installation of cabinets
Finishing of the ceiling
Installation of lights, outlets and faucets
Finishing
Final Inspection
Sea Trials
Yacht is shipped to the major port requested by the customer (There are additional costs for delivery to East Coast ports)
Commissioning/final detailing
** Production time may vary **

|
|

Above: Hull #1 under construction.

Hull #2, 'Perseverance', under construction:
Note the rounded windows throughout & extra storage lockers at the front of the Pilot House

Hull #3 and #4 under construction

|